Project description

Expansion of Warszawa Okęcie International Airport

Time period in which the works were carried out: 2004 – 2005

Range of construction works performed –Terminal 2 basic ground plate
Instalment of thick concrete 2.400 m3
– Inserting the PCV folio under the basic ground plate
– works on the basic ground plate below the staircases and the pump station
– the „Bauma” system in the quantity of 1.500 m2
Installation of armaments 5.500 tons

Concrete works on the basic ground plate, thickness 80 cm, including 13.500 m3 of concrete

Constructor

Client:Konsorcjum FERROVIAL AGROMAN S.A., BUDIMEX S.A., ESTUDIO LAMELA.