An office building, part of the „Polskiej Wytwórni Papierów Wartościowych”, construction of the elevator shaft as well as architectural concrete pillars.

Time period in which the works were carried out: January 2008 – March 2008 Range of construction works performed – carpentry concrete:
Walls, ceiling constructions, beams and monolithic reinforced concrete
– Basic ceiling construction elements – HC plate
– Elevator routes and architectural concrete pillars
– Monolithic reinforced concrete connectors on four storeys that are connecting the existing PWPW building PWPW with the newly built
– Curved covers of the reinforced concrete connectors
– Reinforced concrete pillars and walls
– Reinforced concrete pots with armour plating

Constructor

Client:EIFFAGE Budownictwo Mitex S.A.