Building B of the Rondo 1 Complex – 40 storeys, reinforced concrete monolithic construction connected to the steel construction, building height 160 meters, surface of one storey – 2.000 m2, period of execution of one storey – 6 days

Time period in which the works were carried out: February 2004 – June 2005 Range of construction works performed:
Monolithic reinforced concrete pillars – 1.300 pieces
– Monolithic reinforced concrete ceiling constructions – 60.000 m
2
– Monolithic reinforced concrete walls – 1.900 m
2

Constructor

Client:HOCHTIEF POLSKA SP. Z O.O.